Recommendation: It is recommended that the scheme layout as shown on drawing number EATS(N)403-01-00 be approved in principle, at an estimated cost of 40,000, with scheme details to be approved under delegated powers, in consultation with the local member and chair of North Devon Highways and Traffic Orders Committee.
1. Summary
This report seeks scheme layout approval and estimate approvals for a Zebra controlled pedestrian crossing on Blakes Hill Road Landkey.
2. Background/Introduction
The C783 Blakes Hill is the main route through Landkey and provides a link to the A361 North Devion Link Road from surrounding villages and hinterland. The village primary school is situated to the south west of the road. There has been expansion of residential development to the north east of Blakes Hill and the proposed location for the crossing is at a point which is on the primary walking route linking the residential development with the school.
The provision of a Zebra crossing at this location has been a long standing aspiration and is featured in the school travel plan. The provision of a zebra crossing at this location will improve safety for vulnerable road users and promote safer walking routes to the school.
3. Proposal
The proposal is shown on drawing EATS(N)403-01-00 and comprises a Zebra controlled pedestrian crossing located on Blakes Hill immediately north west of the junction with Barleycorn Fields at the location of the existing crossing point of Blakes Hill.
4. Consultations/Representations/Technical Data
Safety concerns have been raised by the school and local residents who have lobbied for provision of a crossing at this location for many years.
5. Financial Considerations
The preliminary estimate of scheme cost is 40,000. Funding for the scheme has been identified within the 2013/2014 Market and Coastal Towns Foundation Programme of the Devon Local Transport Plan.
6. Sustainability Considerations
The scheme will support school travel plans and encourage walking, contributing towards a positive carbon impact by reducing car journeys.
7. Carbon Impact Considerations
The scheme will support school travel plans and encourage walking, contributing towards a positive carbon impact by reducing car journeys.
8. Equality Considerations
An Equality Impact and Needs Assessment (EINA) was undertaken for the Local Transport Plan. No negative impacts were identified.
9. Legal Considerations
The proposal will be advertised in accordance with the Road Traffic Regulation Act 1984.
10. Risk Management Considerations
Financial risk has been identified and appropriate allowances have been made within the scheme estimate and capital programme to protect the Council's position.
11. Public Health Impact
None.
12. Options/Alternatives
Alternative crossing designs and locations were considered. The indicated location provides reinforcement of the existing crossing point of Blakes Hill
13. Reason for Recommendation/Conclusion
Provision of a Zebra crossing at this location will enhance school and pedestrian links within the village and improve road safety for vulnerable users.
David Whitton
Head of Highways, Capital Development and Waste
Electoral Division: Chulmleigh & Swimbridge
Local Government Act 1972: List of Background Papers
Contact for enquiries: Rhys Davies
Room No. Barnstaple Civic Centre
Tel No: (07967040366
Background Paper | Date | File Reference |
Nil |
|
|
rd111013ndh
sc/cr/landkey blakes hill zebra crossing
02 hq 211013